PROJECT OVERVIEW

The Woolworths Ferntree Gully project demonstrates our capability to deliver high-quality retail upgrades within live operating environments.
Completed over a 14-week program, the works focused on expanding and enhancing an active supermarket while maintaining full store operations.

The project involved the construction of a new precast extension, seamlessly integrated with the existing structure to increase the store’s retail footprint and functionality.
Key works also included the construction of a new cool room, coordinated closely with Woolworths’ Refrigeration Infrastructure (WRI) team, as well as internal store alterations, featuring a new ramp, slab, and Direct to Boot (D2B) extension.

Key Features

  • Construction of a new precast extension to expand the retail floor area
  • New cool room construction coordinated with WRI
  • Internal store alterations, including new ramp, slab, and D2B extension
  • Installation of a structural steel canopy to enhance the façade
  • Delivery of a new roofing system to modern durability standards
  • Stormwater and hydraulic upgrades to support new infrastructure
  • Works completed entirely within a live trading environment

Operational Management

All works were carefully staged and coordinated to ensure no disruption to trading operations.
Proactive communication with store management, thorough planning, and effective noise and safety controls enabled seamless delivery in a live retail setting.

Outcome

The project delivered a seamlessly integrated store expansion that improved operational functionality, enhanced presentation, and supported new service capabilities — a clear example of our strength in delivering complex retail upgrades within live environments.